Friday, May 28, 2010

Day 157: Sparkies on site

Little bit of work done today, with the electricians running in some wiring to the garage now the roof there has been completed. While I couldn't get my 3 car garage, or even a workshop, at least there's plenty of powerpoints and a TV outlet!


Near the front of the garage is a double powerpoint, plus light switches for the ceiling fluoros and an external light.

There'll be two fluoro lights on the ceiling - can never have enough light in the garage for working!

Inside the sparkies have starting locating wiring for powerpoints and switches. We've placed the washing machine powerpoint and water taps on the wall above the machine (hate bending down to turn things on & off inside cabinets!)

Apparently someone from the cabinet company came by to check on the installations today too, and have left this sign:


So while the fixing stage is meant to be complete by 31.5.10 (according to MyMetricon), I very much doubt it'll be complete by then unless teams of tradies work throughout this weekend. The definition of the fixing claim stage being complete is:

"The stage when plaster is hung (decorative cornice may not be complete) architraves, skirting, doors, baths, basins, troughs, sinks, cabinets and cupboards are fitted and fixed in position. Attached garages, front porticos and carports are completed (Granite installation may not be complete). Or percentage of works completed."

Erm... we have no doors, no skirting, no architraves, missing plaster in the kitchen and none in the garage, portico isn't even started and many items from the lockup inspection haven't been addressed - so should we receive a fixing invoice in the mail before these items are completed, there's no basis for us to pay it!

T&T