Monday, August 9, 2010

Day 230: Late meetup with SS

Was on the way home when our SS called asking if we could catch up tonight - we ended up meeting at 6:30 - I guess site supervisors gotta work around the clock! Anyway, it was just to check whether we wanted some extra glass splashback in the kitchen - the standard design doesn't put any glass into the window reveal - despite the fact that all Metricon display homes with a window splashback and glass, have glass that go into the window reveal.



So here's a pic - taken on my new iPhone4 (without the useless LED flash going off, which makes everything look blue). The big glass piece on the side with the powerpoint hanging off it is standard, then there's another small glass piece which goes next to it (but only as high as the window reveal), and then there's "normally" plaster at the window reveal. Our SS thought it'd look better with the extra glass piece in both reveals for about $150.

Sounds reasonable, and we said so at the time - but now I recall then when we signed up with Metricon there was a promotion on for a glass splashback - we paid extra for the kitchen window, about $800 or so, we didn't get any credit back for the reduction in glass splashback (now taken up by the window) and now we pay a bit more, to get that little bit of glass back.... *sigh* ultimately it's not a huge amount of money, but given that we paid for the window, it would've been nice to have been given the glass that goes into the reveal.

Anyway, this certainly isn't a reflection on our SS - we've been quite lucky to have had a couple of very good site supervisors, who seem to be organised, efficient and proactive. Not long to go guys, keep it up!

We also had a quick look around the house - shelves are in, wardrobe fitout in the master bed is in (another item thrown in with the promotion, but it's actually quite a good size fitout with lots of shelves and drawers - happy!). Door handles are on, though the master bed door is meant to have a privacy lock which was put on the ensuite toilet instead - an easy fix, just swap the handles around. Errm.... mirror robe doors are on and look good too! Caulker has been through the house sealing up all the gaps. Still waiting on the rainfall showerhead in the ensuite shower and toilets - they'll both be put in sometime soon. The laundry splashback which is a little short will have another row of tiles added... happy about that too. Cement sheeting has been installed in the garage & portico, so they just need to be prepped and painted, then the garage door can go on. The house has also had a bit of a clean, and looks a million times better than when it's filthy!

Had a little talk about the light position in the sitting room and upstairs leisure - as a reminder, here's the sitting room lights and where they should be...


and the upstairs room lights, and where they should be too.


The thing about the electrical plan, is that it doesn't specify to the millimeter exactly where things should go. Now that allows for variability in the house construction process - for example, presence of studs or trusses etc, however I don't really think that's an excuse to stick a couple of lights obviously off-centre in the sitting room, or to put them a meter from the expected position upstairs. We did adjust the upstairs light position with our previous SS, and as to be expected not all changes or agreements are communicated to the following SS.

Still... all we want are our lights to be centred! Doesn't seem to be too much to ask. The electricians managed to do it everywhere else, but had a bit of a brainfreeze when doing the sitting room and upstairs.

And coming back to completion date, we had originally pencilled in Friday 20th August for a completion inspection, but might have to put it back to Tuesday 24th. It's very difficult for me to arrange a day off work, so let's hope this is the last adjustment of date. That said, we're not in a huge rush to get in our house - provided it's of a high quality finish (and YES that includes putting the lights in the centre of the room, not 40cm from a wall!!) we don't mind waiting another week, fortnight or month for the completion inspection. However it seems that head office is pushing for a completion this month, and providing quality doesn't suffer, we'll certainly be happy to have our house done!

Also need to organise carpeting - got a quote from Fowles flooring in Clayton for 40.5 lineal meters of carpet - enough for all upstairs and the home theatre room - for a dark grey carpet, so I'll head down there tomorrow to confirm everything and leave a deposit. Not sure if we'll have the carpet done before handover, but it won't be long after anyway, apparently there's a few days to have the carpet in stock, and about 2 weeks to book an installation day.

Finally for today, reminder to self: check the final invoice thoroughly! It'll be for the remaining 10% of contract value, plus our electrical upgrades, plus tile upgrades, minus an amount for an underground powerpit which we organised and paid for ourselves, and minus an unknown amount for "cranage provision". Also a credit amount for changing to a different toilet than originally selected, and a little more for that glass splashback extension.

Phew, gets complicated! Will also need to have a thorough re-read through the contract and see if there's any other provisional items we may be entitled to.

If anyone has had handover on their house, please comment and let us know what to look for, tips and tricks are most welcome!

T&T

Tuesday, May 25, 2010

Day 154: More waterproofing

Some more waterproofing - at least I think that's what all this blue stuff is.

Around the ensuite bathtub. Colour actually looks quite nice!

And also in the bathroom around the shower & bathtub. If you look at the shower base, you can see a little white lip, but this should be hidden by the floor tiles.

Trying to organise a meetup onsite with our SS for next week, as according to MyMetricon, we're meant to be finished the fixing stage on 31.5.10 - and then we're onto the final stage! Though what we are trying to find out at the next meeting is what's happening regarding our independent inspection items, as they really need to be fixed before any further work is done in the next stage. We've paid all our stage invoices on time up to now as progress has been OK, but the fixing stage invoice for 20% won't be paid unless we're happy with how the issues identified so far will be rectified. They're not particularly difficult to fix, but not much has been about them as far as we know!

T&T

Friday, February 19, 2010

No work on our house today - let's dissect a Tribeca in this blog post!

No further work done on our site today, probably awaiting delivery of a few more bits & pieces.

Anyway, Tina found a Tribeca that's going for sale nearby in a few weeks time. Let's do our usual critique of the house!

(disclaimer; all the opinions expressed below are tim's (as tina prefer to stalk blogs, but not post anything) and I'm not a qualified exterior/interior decorator - though I can get pretty bitchy sometimes as you've probably worked out!)

Now this house was constructed fairly recently - looks like a Kingston facade. Note that on the M website, pretty much all their facades show render (extra cost!), whereas this Kingston facade shows face brick. Perhaps a little overwhelming with just brick everywhere - a rendered balcony would add a bit of contrast (or even stackstone?). Also note there's a wood feature entry door but also wood french doors to the balcony (but black aluminium windows elsewhere). Perhaps a bit unbalanced - consider doing ALL windows/doors to facade in wood, or a feature entry door and aluminium elsewhere (what we're doing) but maybe not a mix & match as shown here. There's also a contrasting gutter to fascia; a fairly minor detail. Doing the fascia in a lighter colour (to match the eaves) makes the gutter look a little smaller. Over the garage door is a painted beam, whereas nowadays most M double storey houses have brick infill over the garage door. In the front yard, the garden retaining walls match the driveway colour, and an abundance of plants means no lawn to mow - yay!


This open sitting room at the front of the house is a great feature to have - useful for greeting guests, and for sitting (of course) and talking. The fireplace there is around a $7k option nowadays - of course, if you don't option a fireplace here, you could always put something in its place, like a TV or display cabinet, or a painting. In this case, the fireplace and the painting are fighting for space - looks crowded in there! Nice Roman blinds are a great modern and minimal window treatment. Not real keen on the tiles and timber transition - why not just have all tiles, or all timber? And I'm not sure the light timber colour is a complementary colour to the grey floor tiles. I do like very much the grey walls in the hallway though, it's nice to see some cool neutrals on a wall rather than the usual creams/beiges, a little unusual but definitely modern. Checking the staircase, looks like stained hardwood treads - instead of a carpeted staircase, where the carpet tends to look very ratty after a short period of time from constant up/down trampling.

Finally, the master bedroom. This is actually kind of similar to our master bed layout (though for those of you who have scrutinised M designs, they tend to replicate layouts with slight variations across the whole range). The feature false wall has a couple of reading lights mounted into it (nice touch!) plus a cutout or niche for displaying things. Behind the false wall is a walk-through robe, though it looks like there's no doors at all across the robes; which of course means your mess of clothes is on display in photos like these. Trade this off with convenience of access to clothes (no doors or sliding doors to move first). The ensuite has a wide opening (trendy and modern) but we've closed ours off with double cavity doors for privacy. And again, the side walls are a light grey shade compared to the white ceiling - this look is growing on me (but we've already picked white ceiling and white walls, but at least we could always repaint later!)

Anyway, we'll be at the open for inspection this Sunday. But it's available for plenty of other inspections - want to find out when, click this link! Asking price is around $1.05m - the location is great and it's got a lap pool, but I'd like to know how much land it's sitting on before figuring out whether it's a worthwhile figure or not.

Feedback section now, replying to previous comments on earlier posts...

paul: You're right we didn't sign the prelim contract on the day it was presented to us. Mainly because it'll take your CSC at least 1-2 hours to go through it, and we knew we had heaps of changes we wanted to make. When things were almost 100% as we wanted it, then we paid the next deposit stage and moved on. You can still change things after signing & paying too.

sean: Good advice about putting things in writing and copying it around. We're not too fussed about frame issues right now as they're minor and easily fixable, but we'll get a list in writing to check at the frame inspection (plus an independent inspector at lockup). Our SS seems well organised but (like yours) a little uptight. I'm still hoping to run some speaker and projector cables through the frame on the sly, but if it doesn't work out, I've got a backup plan!

T&T

Thursday, February 11, 2010

Day 51: Wild weather, but trusses about 80% complete!

Woke up this morning and happy to see clear skies and warm weather. This all changed by about 4pm, when the skies turned black and solid sheets of water fell from the skies - cutting out power to my office block, so I left early to check on the site.

And happily it appears the chippies were able to get a heap of work done in the morning prior to the storm - lots of trusses installed, maybe 80% complete? Just trusses over the sitting room and entry gallery to be completed.



Only had time to take a couple of photos on my iphone before the rain went mad again - here's a pretty wonky photo standing in the hallway ;looking towards the back of the house - study is to left, laundry to right. Void in trusses for the future staircase. Having the trusses in lets us get an idea of how large the rooms will really be. I'd highly recommend to anyone building a house to upgrade to higher ceilings if your budget permits - you definitely can't add this later on, and it gives a much more spacious feel to the house! I've heard of huge variations in how much builders charge for higher ceilings. I think ours were great value, only about $2000 more for 2.7m ceilings to the ground and I can't remember how much (less than $2k) for 2.55m ceilings to first floor (Metricon apparently don't offer higher ceilings than this for ground & first). One builder on H1 wanted $10k for 2.7m ceilings to a single storey house - wow!


The pic above shows floor trusses in open plan rear area - the kitchen area is covered by trusses, the open area to the left is the dining area (no first floor above here). You can see two pipes for the kitchen sink, but for some reason there's a big pipe near the frame and we can't work out what it's for - there's no plumbing void marked on the plans, so we'll ask our SS next week about that.

Hoping the weather will hold off tomorrow morning so the remaining trusses can be installed, and maybe the start of first floor trusses, though maybe scaffolding will be needing.

And for anonymous who wanted to know what the payment breakdown is, it's like this:

  • $1000 initial deposit; covers site survey and soil test (well, it did for us anyway)
  • $3000 at preliminary contract acceptance to cover cost of custom plans
  • 5% (less the previously paid $4000) at contract signing
  • Base: 20%
  • Frame: 20%
  • Lockup: 25%
  • Fixing 20%
  • Completion 10%
Now that we've started along the journey, it's plain to see the payments are clearly biased to having most of the money upfront -ie by the time you get to lockup you've already stumped up 70% Perhaps that's why (for most builders not just Metricon) the first 3 stages go by quickly, then things tend to slow down at fixing & completion. Would be interesting to hear if anyone has successfully negotiated different payment percentages? Of course, ultimately you end up paying 100%. Also, note that things like postcontract variations are added/subtracted on you completion payment - we'll have to pay about $15k more for various additions, less $1000 for power pole, plus $x for retaining wall and whatever other little things turn up.

Anyway, we're pretty happy about progress on the site - at the start of last week we had a few plumbing pipes in the ground, now we're starting on the first floor frame! Providing the weather holds off, we're fairly confident our SS's predictions of frame completion by end of February will work out - and of course, another bill for 20% of the build in our letterbox!

T&T

Friday, February 5, 2010

Day 45: Base invoice received

First of all, let's go on a minirant here about HP/Compaq and their shitty quality products. You'd think a multinational brand like HP would be able to build a laptop that doesn't break their hinges after a few months, randomly freezes, loses sleep/hibernation modes and have a battery life longer than 50 minutes, but apparently not. And let's not talk about the fact that HP have decided that a 2 year old laptop (that was top of the line when new) is simply waaaaay too obsolete to be worthwhile supporting under Windows 7. End result, don't trust, buy, or recommend HP/Compaq. Meh! My old Acer laptop is still used by my sister with 100% reliability; and I bought that one in 2002 - far superior.

Aaaaaanyway....got an express post envelope from Metricon today, with just a few pages, but a big bill to pay - 20% of contract! It's interesting to note though, that the progress payments are based on the contract price that you sign off on, at the final contract meeting. We had about $15k of postcontract variations (mainly electrical, roof tiles, tile upgrades), but they will be added to the final invoice, along with any other changes that may come up along the way.

No work done on site today - weather in the low 20s and constant light rain. Again, good for concrete curing, but not so good for deliveries or getting work done. Maybe some framing to start next week?

sarahv: yeah, the old house was a nice house to live in - unfortunately it was on a very busy road, right next door to a petrol station, opposite a big bunch of units. Not a great location for a residential property, but not too bad for a medical clinic! Would have liked to have the house and land (about 700m) in a different location, but alas not to be. Fond memories, but can't wait for our dream house to be finished!

Wednesday, October 28, 2009

Building Permit Approved - 4 days in council, is that a record??

So things are really starting to happen now!

We received our "final" construction drawings last week, but had to correct a few things:
- ensuite had shower rail and rainfall head together, instead of at opposite ends of the double shower
- powder room door swung wrong way
- Light switch placed behind door
- some electrical items at wrong height
- added note that benchtop runs all the way to window splashback

and after 7 goes at getting it right, we finally signed off on the correct drawings yesterday!

We also received word that our building permit was approved - it only took 4 days! It helps we already did the legwork to get the building over easement approvals months ago, and that alone took 3 weeks for a rubber stamp! Our CSC says they use a private company to submit the approvals, and providing the siting and design is done in line with Rescode (which our house complies with) there is usually less than a week to approve the build.

We also received our plans in the mail yesterday with the energy assessment, and apparently we've got a 5.5 star energy rated house, which is nice to know! Didn't really design the house with energy rating in mind (even added a couple of windows on the west side, which is meant to be a no-no).

We're still waiting on our tile appointment results, about $2000 worth of feature tile upgrades. We were lucky enough to be able to use the original Metricon/Beaumont tile selection range instead of the reduced range brought in around August. We upgraded to a nice mosaic tile around the powder room mirror, the same mosaic in the ensuite shower niche, and also an aluminium stripe around the fully tiled ensuite. Will have to upload photos, but Tina has the tiles at her parent's place.

On other things related to the redevelopment:
- power pit being installed today - they say! We paid for this September 23 and was meant to be done within a month, but some delays here for whatever reason.
- Temporary fence for the demolition is being installed Friday. The annoying thing is that virtually all fencing companies will quote for a 6 month minimum, and they all want about $350 - all we need the fence for is 2 weeks or so!
- Demolition booked for week after Cup day - I hope they can start earlier, as we've got the fence up early, but it's all up to their schedule. Need to have a completion date before we can get a re-establishment survey completed.

And hopefully we'll be in the clear with a week to spare before penalty delay payments kick in!

Maybe the next time we post, it'll be with demolition pictures!

Friday, October 23, 2009

Construction drawings received, building permit applied for!

So yesterday afternoon (Thursday) we received an email from our CSC with our final construction drawings, and a standard email saying that we're to check they're correct, sign and return. With the additional line "Please note no changes or alterations at this stage are permitted"!

Anyway, we had a look through the plans and found a few errors, including:
  • Laundry and powder room tiling not shown
  • Wrong exhaust fan to powder room
  • Data and cable internet access at wrong height
  • FC infill noted where brick infill is
  • Powder room door swings open the wrong direction
and the big one, a muckup in the ensuite shower layout. We swapped around the WC and toilet in the ensuite, so we could get a bigger shower (1600x900) and added a rainfall showerhead in. Anyway, the ensuite elevations were all screwy with the showerhead and rainfall located in all weird positions.

So we sent an email to our csc last night noting these errors. We got an email at 9:30am today saying she was on the case, and revised plans sent through 30 minutes later. Way to go Mendo!

Unfortunately there was one issue now caused, by correcting the powder room door swing direction, the light switch ended up behind the door. So sent another email through, and true to form another revised plan sent an hour later.

Now maybe we're just extremely lucky, or Metricon are desperate for us to sign & approve the construction drawings, but today we've had nothing but excellent service from Mendo and the Metricon drafting team - keep it up guys & gals!

Anyway, by the time I had time to check my email it was after business hours - things look good on the plans now, so we'll sign this weekend and email it back to M.

On other news, "My Metricon" has had a few updates;
  • Finance approval has been received
  • Sewerage/water permit has been approved
  • Contract engineering is completed
  • And Building permit has been applied for today! And Building permit approval is expected to be Oct 28!
Honestly, a few nights ago I had a dream (no joke) our slab was done, and I was walking the dog around it... can't wait for that to come true!

still waiting for our tile selections and costing to be finalised and emailed to us, though we're not sweating on this one, as it's not critical to the initial build stage. I also called our demolition crew to see if they could start early, seeing as the old house is deserted now, but they're flat out with other work and will hopefully start 2nd week of November as planned.

Anyway, the main message here is rule #1 for all home builders - READ, CHECK, RE READ, RE CHECK all your documents and plans before signing anything! And once you've done that, read and check again! Unfortunately I have this niggling little worry that no matter how thorough we think we've been so far, there's probably been a few glaringy obvious errors that we won't become aware of, until they become a problem we have to fix. But that's the fun and risk of building!

T&T

Monday, October 19, 2009

Old house being stripped - nearly done!

So, last Friday I had the evaporative cooling unit, pipes, remote control and vents all yanked out of the old house and stored in my parent's garage over the weekend. Was all installed today, so thankfully should have some relief for the upcoming summer heat!

Finished moving things out of the house yesterday too, thanks to my uncle and his delivery van! The only thing left in the house now is dust, asbestos, and a few squashed spiders!

Also made a few phone calls today to check on how everything is progressing for the pending demolition of the house.
  1. Electricity has been fully disconnected - meter is gone and overhead power line cut off.
  2. Gas: Called to check the service pipe has been disconnected - yep, not a problem!
  3. Underground power pit: was paid for at the end of September, and the operator advised me the installation date is tomorrow, so I'm hoping to go by the house in the afternoon and see $1600 worth of electrical manhole in the pavement!
  4. Beaumont Tiles - some thorough readers may remember a while ago when we first saw the M tile selection, it was HUGE, and then a month or two after, it was NOTHING (literally, from a selection of over 100 tiles, to less than 15!). I raised this point with our CSC<>
Finally, in the afternoon today Mendo sent us the revised copy of the preconstruction variations, which we'll sign off on tomorrow and email back to her.

I'm hoping that once the powerpit is installed, I'll organise some security fencing and give my demolition guy a call, and hopefully might even start on the demolition earlier than planned!

Stay tuned, for tomorrow afternoon hopefully we can post tile selection pics!

T&T

Tuesday, October 13, 2009

Final contracts - SIGNED! Now we're really on the way!

So we had our contract signing appointment this morning, it went quite smoothly, to be honest!

Of the big email we sent on the weekend, pretty much everything has been addressed.
  • Cat 4 bricks to whole house - done (additional $1000 or so as they only quoted to sides & rear before)
  • Changed to the biggest Clark double undermount sink (the Razor series, which for some reason doesn't work on their website properly) - done, and was cheaper by $100 than the ePure series sink!
  • Chose different trilock door to internal access - done
  • All the minor drafting errors - to be corrected by construction drawings
  • Electrical plan - hopefully coming this week or next.
The only thing was that with our fancy cantilevered stairs, there's not much room under the stairs where I had planned to stick the TV splitter, patch panel, modem etc, so we've got rid of that idea and stuck everything up in the walk-in linen cupboard. Paid up our 5% deposit less the $4000 paid to this point.

Now all we have to do is send in our signed loan documents (we were meant to have them last week, but still nothing, so I'll have to give our broker another nudge to find out what's happening), and sort out the demolition. The evaporative cooling is being removed this Friday and hopefully installed in my parents house on Monday, and I think I can get all the remaining furniture out in one day, as there's not much left.

And as for the fine details, estimated days for completion is about 370, so we're hoping to be in by xmas 2010!

T&T

Friday, October 9, 2009

Final contract received - post contract variations?

Our CSC called me this afternoon to let me know the final contract was going to be emailed out soon (we had it by 5pm), the only issue is that our electrical plan isn't done. This is because we only did the electrical appointment 10 days ago, and they're taking their time getting the drawings done - but she said we can just add it on as a variation after the contract is signed - how does this sound to everyone?

Otherwise, the contract and drawings were done pretty well with only a couple of issues to address, such as;
  • We want Cat4 bricks to the whole house - in the contract, we've only got Cat4 bricks to sides & rear. Wonder what can be put on the facade, if not bricks?
  • 2365 framed mirror doors on plans are marked down as only 2065mm high
And for a few very minor issues, the glass splashback is smaller than we thought (200mm high instead of full height) - since we have a big window splashback it's not a big deal, but we'll ask about it. Also, we added in at late notice a trilock handle to the internal access foor from the garage, but it's a knob instead of lever, and it might be better as a lever to match the other door handles.

One nice thing is that we asked for an additional rainfall showerhead to the ensuite, and we ended up with 2 rail showers and a rainfall showerhead - it looks excellent on the plans, can't wait to get using it... in 15 months or so, or however long it'll take to build!

I guess the main thing on this final contract, provided our CSC says our electrical plan goes through as a normal post-contract variation (with no further penalty fees to pay, since it's not our fault they haven't got the electrical plans drawn up properly) then we're pretty much set to go for contract signing on Tuesday.

Just got to prepare payment of 5% less the $4000 already paid (I wish they took amex, all them credit card points would be worth something)! So, bring my chequebook, copies of bank statements as proof of funds for half the build, call my demo guy to get a copy of demo permit for M, and a big fat pen to sign a thousand pages. We were meant to receive our finance approval today, but it hasn't come through yet - if it doesn't come on Monday, I'll call our broker again to get a hurry up!

And drove by the old house a few days ago, the overhead power line has been cut, so just the gas service line to be removed, and evaporative cooling to be relocated.

If anyone has any comments on how to approach final contract signing please let us know!!

T&T

Monday, October 5, 2009

HIA contracts vs Metricon contracts; what should we do?

Well, the time is rapidly approaching for our contract signing appointment, which is booked on Oct 13th.

There are a couple of minor issues we're dealing with tonight!

1) Finance. We've been approved for a Line of Credit to pay for half the house build; which we're still waiting on the final documents to sign. I'm wondering how long it'll take Heritage to turn around everything, as we need to provide proof of financing within 14 days of contract signing (ie by Oct 27th)? But in earlier communication, our CSC said all we had to do was provide a copy of loan preapproval at contract signing, with full approval due within 30 days of contract signing.

2) Demolition. We've booked it in for November 9-13, and the HIA contract states it needs to be done within 30 days of contract signing. I'm thinking it's cutting things a little fine here, just in case things don't go according to plan!

And in addition to all of this, M states that "the contract must be unconditional within 150 days of deposit", 150 days being November 24. What I imagine is that the HIA contract isn't unconditional until all finance is approved etc, which I imagine means we need to sign up by end of October?

Confusing! Anyone got any advice re financing, deadlines etc, please comment!

Anyway, my plan tomorrow is to;

1) Call Heritage regarding loan paperwork
2) Call Telstra regarding a telephone line that's still obviously physically connected to our house, despite an operator telling me last week that it had been disconnected
3) Call the demo contractor to check on dates (and in particular when will it be finished) and maybe try to book them in a bit earlier

And here's some pics for you, as we know pictures tell a thousand words! Here's the glass/stainless steel rangehood we changed to:

Here's a pic of the ceiling mounted rainfall showerhead that we've put in the ensuite shower, in addition to the rail showerhead. Expensive, but they're worth every penny to relax after a long day at work!


Phew!

T&T

Tuesday, September 1, 2009

Preliminary Contract & Variations Signed!

Ah, it's nice to feel that real progress is being made! We went to meet our fantastic CSC this afternoon to go through the Preliminary Contract and Variations, and now it's all signed and further deposit paid, we've settled all our structural changes.

Want to know what they were? These are the main ones...
  • 2700mm ground floor ceilings, 2550 first floor ceilings and 2340 doors everywhere including a bunch of extra doors closing off the study, gallery, ensuite.
  • Revised powder room layout: WC and vanity in one room.
  • Revised laundry layout: big walk-in linen and moved door opening, bonus of now having a massive fridge recess for a fridge and 2 wine fridges :)
  • Revised ensuite: swapped toilet & shower, now we have a huge 1650 shower! Got to remember to option in a rainfall showerhead too!
  • Brickwork infills, 600mm eaves, fancy cantilevered staircase, horizontal feature window to wall of sitting room, window kitchen splashback, centred rumpus rear window, fridge water point, extra external taps, rear garage roller door
We've still got a lot of upgrades (I'm sure!) to spend more money on in the colour, electrical and tiles appointment, but this is going to be our dream home, so why not?

On other important issues, contacted Jemena/United Energy this morning regarding the power pit. Single phase is about $800 and triple phase $900, so we'll just go for the big bad boy up front. Plus maybe another $400 in longer cabling cost? Has anyone ever put in a power pit, as on the application form it says we need to name a Registered Electrical Contractor - I thought United Energy handled all of that?

On the demolition front, it's been about a week since our demo contractor (hopefully) put in the demo permit. Good news is we don't need a tree removal permit though. Hopefully this clears in the next 2-3 weeks.

We also submitted a "Building Over Easement" application last week, again another 2-3 weeks should see the result of that.

Looks like we'll need to start organising disconnections of gas, phone and electricity, as it's possible we may have a November start date!

And on the colours front... does Austral Hawthorn 50mm sound familiar to anyone?

I think this is from one of the Berwick display homes. The 50mm brick looks fantastic - very upmarket, and perfectly matches with flush white mortar. We'll match this to light first floor cladding and a feature render to the balcony & portico!

T&T

Saturday, August 15, 2009

Preliminary Contract received by email yesterday - a LONG post!

Well, our preliminary contract meeting is for Tuesday Aug 18th - we received a copy of it by email yesterday.

It contained details on the floorplan, facade, overlooking, overshadowing etc, plus a more formal documentation of all the upgrades and promo items, and of course - site costs!

We were informed of approx $30k in site costs, and it's a few hundred bucks more than that in total. Includes such charges as;
  • Cut & Fill 3k
  • Slab upgrade from M to P $7k
  • Redevelop costs $7k - additional survey, site cleans, temp fencing, traffic management, protection to adjoining houses etc
  • Reconnection to sewer $750
  • Cranes $3k
  • Double handling $2500
  • Termite protection $1500
  • Underground power pit $5k - we might arrange this ourselves, apparently the true cost is about $2k if we organise it!
  • Temp power pole $1k
However, there are a few things which we weren't particularly aware we had to do - perils of building for the first time I guess! Including;

1) "Owner to apply for "Report & Consent" from relevant authorities for building over easement. "Report & Consent" to be applied for prior to building permit application. Customer to be aware that this item does not constitute approval, therefore siting is conditional on approval. Owner to apply to local authority to obtain neighbours names and addresses prior to M homes making application".

We have a 1.83m easement along the back which isn't a problem, but also a 1.83m easement along the side, and currently our siting puts the house approx 2.055m from the boundary. So I have a few uncertainties here;

a) Do I have to get all the approvals from Yarra Valley Water and local council? If so, do I have to do this prior to signing the preliminary contract, or can I do it before signing final contracts?
b) Is there any risk that this will be denied (and then throwing off the whole building process?) We don't mind so much if there's a little extra cost in piers or whatever else is structurally required so much.

We did post this question on Homeone and here's a reply we received - what a source of knowledge that forum is!

"Hi sklnv,

Which suburb are you building in? How many pipes do you have in your side easement?

We have a plot of land in SE suburb within Monash City. Our land has a 3m wide drainage easement running along the side boundary. Easement has 2 pipes, one belonging to council and one to Yarra Valley Water. We had faced a similar situation (except that we weren't going to build over the easement but near to the easment) and had a previous knockback with council's engineering with a previous design which saw the house sited 50cm from the easement and the builder having to dig into the easement to take some land from there to fill other parts of the site. Engineering disallowed this cos' the council's pipe was rather shallow in the ground and old too. Luckily, we were only at the pre-contract stage (Tender) and could walk away unscathed. With this knowledge (council not approving siting near to the easement), we knew that we had to be at least 1m away from the easement for the next design we could find for our land.

Now, we have signed with another volume builder to build our house. We applied for consent to Yarra Valley Water to build close to the easement (our siting of the house is 1 m away from the easment and their pipe lies 90 cm from the side boundary). We did this before signing. We were given approval by Yarra Valley and this only took a few days (even though they said it could take up to 2 weeks for processing). You would need to supply Yarra Valley with a copy of your prelim site plans when making your application and a small fee is payable. Since Monash city owned the storm water pipe (the second pipe in our easement), we spoke with the council's engineering dept - brought in all documents (i.e site plan and engineering computations). The engineer gave me the all clear and said I didn't need to make any applications for consent.
You can always start making your enquiries now with Yarra Valley and your city council since it can take time for processing of the applications. With council, they would need to advertise your report and consent application to your neighbours - 14 days advertising period and than some days to make a decision (ours took 2.5 weeks only in total). Even if council indicated to you that there wouldn't be a problem for you to build over the easement, it only takes one neighbour to raise a valid objection for you not to get consent! You could appeal against a rejection of your consent application but this is with another division. (In our case, we were lucky that we got consent for a reduced front setback despite one neighbour objecting. The assistant building inspector said that my neighbour's objection wasn't valid to our application. Neighbour said she was concerned about loss of sunlight to her verandah. For us, the drainage easement and an angled frontage worked to our advantage in order for us to have a reduced front setback! phew)

The other thing you would need to find out is the depth of the pipe(s) in your easement. If they are not very deep, you may get an objection from either the Yarra Valley or the council. The best really is to contact Yarra Valley (for depth and location of their pipe in the easement) and your city council for advice. Yarra Valley in our experience has always given us a prompt reply. They emailed to us the location and invert depth of their water pipe to us. Yarra Valley would also probably tell you to submit an application for consent to them.I can't remember whether we had to pay for this info though. You would probably be able to get all your questions answered by your city council on the day that you pop into their office to speak with someone from Ton & Planning (and engineering if there is a city pipe in your easement too). The one thing that Town & Planning will say to you is that they can't commit to an answer. You just need to persist (gently) with your line of questioning....in order for you get as much information as possible.

Hope this helps."
What a useful bit of info! We're planning to go straight to the council and Yarra Valley Water after the prelim contract meeting to get this sorted out. This is one item I wish M had informed us of weeks ago!

Anyway, there are a couple of other items we have to organise

2) Ask neighbour's consent to knock down the bit of fence where our garage wall will be, as it's closer than 150mm to the fence/boundary. Will have to ask the neighbours (who are renting) the details of their landlord.

3) Organise demolition approval - which needs to be approved prior to M submitting the council building approval. Again, we could have been told of this a month ago?

so a bit of a downer to the start of the weekend with the realisation there's a lot of work we have to do fairly quickly. In order to avoid delay fees of about $1800 per month, we have to have the final contract unconditional by November 24 - which means we have to sign & pay the 5% deposit on final contract a month before that ie October 24.

Worst case scenario; should building over the easement not be approved, or the neighbour disallows the fence to be knocked down, or demolition approval not given - we might just have to walk away from the current contract with M and start again with another M house design, or simply restart again at a later date. Let's hope it doesn't come to that!

Anyway, to finish with I know we all like to see pictures, so here's a model I did of the house from the back view, with dark brown bricks (and watertank & side fence!). Thanks to Michelle for posting brick upgrade prices!!


Also as promised, Jo recommended we draw up any kitchen redesign plans. Here's one showing our preferred layout for pot drawers (heaps of them!) to the side kitchen bench, and an additional door to the island bench.


Anyway, if any reader has advice regarding demolition companies, applying for building over easements, and dealing with neighbours and fences, please leave a comment as everything helps!

T&T