Tuesday, June 8, 2010

Day 168: Some further plastering/carpentry, and onsite meeting with our two SSs

This morning, the carpenters were in and added the missing noggin in the garage (only 1 required, not 2 because they're only for plaster fixing), as well as installing the balcony!


Plus some other carpenter type things were done, installing/closing gaps around the front door and internal access door with timber strips (that will be stained/painted to match). Now, if we only had a key for the balcony french doors (below), the waterproofers can go and waterproof the balcony so the tiling, guttering, and portico plastering can be done.

Also had a plasterer in today, installing the plaster under the top flight of the stairs and tidying up some other spots. He also repaired the two holes in the ceiling where the carpenters tried to find the damaged floor joist to repair... more on this later!



I guess the big things for today was our on-site meeting with Monique and our new SS John. MyMetricon was updated yesterday to say we were getting a new SS; because Monique is so busy with all the Balwyn builds, John will take care of us and our neighbour down the road (who just had the slab down for their Chelsea - congratulations guys!).

So anyway, we had a page of things that we were mainly concerned about and wanted clarification before any further work was done, and happy to say that we're satisfied with how things are being assessed and fixed.

1) Damaged floor joist: I pointed out to John that the damaged joist was directly under where the upstairs WC waste pipe was located. Since the carpenters had already tried twice (and failed!) to locate the joist from the ground floor, John got upstairs and banged through the plaster adjacent to the waste pipe, clearly marking out on the kitchen ceiling where the joist needs repairing. Should be an easy fix now!

2) Kitchen problems;
  • Kitchen stone bench on the side will go right into the window splashback reveal as per the earlier pic posted- carpenters will cut out all the wood/plaster that's blocking the benchtop.
  • Gaps, missing laminate strips - will all be fixed when the kitchen people come back in for the benchtops, or by the painters. Pretty minor but annoying stuff.
  • Rangehood: Will be externally ducted, will be dealt with later during the electrical final fixing.
  • Cables from the walk-in-linen - to be repaired by plasterer where they've been incorrectly pulled through in the fridge alcove.
3) Laundry waste: Been in the wrong spot for months, but the plumbing people responsible are aware it needs to be moved before tiling.

4) Garage internal access door: A replacement Balmoral-2 door has been ordered, as there was an estimating error somewhere - someone forgot to count all the doors correctly! And the missing noggins have been fixed this morning.

5) Rumpus room doors - Will leave them hanging the way they are, as they're set up for "right handed people" the way the right door opens. Not a big deal ultimately.

So, looks like things are geting back on track! John used to be a painter apparently, which should be a good thing, if it means he has an eye for detail!

The plans for the next few weeks:
  • Carpenters back in sometime this week to do the final fixes and repair that joist
  • Painters might start next week, and take around 2 weeks to complete internal painting
  • Tiling around the start of July
  • By August, final fixings, and maybe firming up on a handover date by that time too!
T&T

No comments:

Post a Comment

LinkWithin

Related Posts with Thumbnails