Monday, May 31, 2010

Day 160: Doors & skirting installed, fixing inspection items

Carpenters on the job today, with almost all the internal doors hung.

First of all, our front door has been installed- a Corinthian 6G in 1020mm wide. Will be stained dark, with a 750mm pull handle and mortice lock.

Next up; home theatre doors. I actually wanted the doors hung opposite to how they are in this pic: if you look closely, the right door has the opening handle, and the left door has the mushroom stop.

I did mention to our SS that I wanted the doors hung the other way - admittedly on the floorplan, they're drawn to this specification. I wonder if it can still be fixed - would involve moving the mushroom stop to the right side door, taking out the handle mechanism from the right side door (and filling in the gaps), and putting it on the left side door.

Upstairs now, this shows the upstairs linen closet. For some reason we had to choose totally different handles for linen doors (we chose rectangular handles that match the vanity handles) as you can't put the door handles you use on normal doors. No big deal I guess. Can also see the architrave & skirting all around too.

The other thing too is that the internal access door is a plain flush door, but we specified at our colour appointment that all doors are to be Balmoral-2 design - we think someone at M head office counted the number of doors wrong! Will contact our SS to see if the missing door is going to turn up soon.

In addition to doors & skirting, a couple of the inspection items are starting to be fixed, yay!


Above, Item 17. The noggin in the wall of the kitchen, below the stair case, has been removed. A small square of plaster has been cut out, and the noggin replaced. Should be pretty easy for the plasterers to seal it back up. In addition, all the data cabling etc is poking out on the left side of the pic - this pic shows the fridge alcove, and the data cabling should be on the other side of this wall in the walk-in-linen. Easy enough to plaster over though.

Another item has been attempted to be fixed...


12. The sewer waste pipe over the kitchen area has been installed through the top flange of the smart joist. The manufacturers of the ‘Smart Joist’ do not allow cutting out of the top flange as noted on their ‘SmartJoist’ hole chart. Recommend the manufacturers supply a rectification design for the damaged floor joist.

Looks like the carpenters aren't exactly sure where this sewer waste pipe defect is, so this cutout in the ceiling is in the wrong spot. To make it easy for the carpenters to find the spot, they should go to the upstairs WC and poke a long drill bit directly adjacent the the waste pipe, and where it pokes through the ceiling is where they need to fix the defect - but I don't want to tell anyone how to do their job, so maybe we'll just sit tight and see how they go about fixing things! Ultimately the ceiling and kitchen needs to be replastered as most of the defects are in this area so the end result will be good - we hope!

T&T